This grass roots project consists of 19 contracts to date including the Main Pipe Rack - Structural Steel & Piping, OSBL Pipe Rack - Structural Steel & Piping, Dock Facilities, ISBL work including equipment setting, steel erection, and piping installation. This project includes the installation of approximately 4500 tons of structural steel, 280,000 LF of pipe and the setting of 240 pieces of equipment.
Several large pipe bridges, including one spanning 210 LF weighing approximately 152 tons was installed utilizing two 500 ton cranes. Approximately 52,000 LF of pre-insulated pipe ranging from 4" to 12" required delicate installation.